P899 SOF Operations Facility

 
 

Naval Air Station Oceana – Virginia Beach, VA

Heard Construction was proud to be an integral part of this 322,436 GSF project that accommodated the Special Operations Command Unit (P-899).  This tremendously large footprint included 185,00 S.F. of Slab on Grade and 143,700 S.F. of Slab on deck construction, heavy duty concrete paving, cast in place vaults, hardscapes and walkways. The project was a very successful one for Heard despite the magnitude and the fact that the site was located on swamp land.

Project Information:

Architect: Waller, Todd & Sadler
Work Self-Performed: $2,591,835.00
Project Manager: Andy Williams
Superintendent: Danny Nero, Theron Sweeney
Prime Contractor: W.M. Jordan Co.
Project Completion: August 2010
Challenges: Site logistics and magnitude

Reference Contact Information
Prime Contractor: W.M. Jordan Company
Contact: Ron Lauster, P.M.
Address: 11010 Jefferson Avenue, Newport New, VA 23601
Phone: 1-757-596-6341
Email: rlauster@wmjordan.com