Heard Concrete is currently working on two new cast in place concrete magazines located at Chambers Field, NAS Norfolk. This project also includes the installation of multiple support buildings with monolithic slabs on grade.
This project has provided us a challenging build and increased our skills in heavy formwork and shoring. Our superintendents have the experience, and it shows in the expediency of construction and quality of their work.
This project also includes heavy duty concrete paving, cast-in place trench drains and various civil concrete.
Project Information:
Architect: Naval Facilities Engineering Command – Mid Atlantic
Final Cost: $31 Million
Project Manager: Andy Williams
Superintendent: Danny Nero, Chris Swartz, Ronald Reinert & Josh Johnson
Prime Contractor: Whiting-Turner Construction
Project Start: May 2022
Project Completion: 2023
Challenges: Inclement weather, winter construction
Reference Contact Information
Prime Contractor: Whiting-Turner Construction
Contact: Dan Hendrick, Project Manager
Address: 6305 Ivy Lane Suite 800, Greenbelt MD 20770
Phone: (252 626-8130
Email: Daniel.hendrick@whiting-turner.com